Step 9a – Install Blocking and Plumbing

Step 9a – Install Blocking and Plumbing

Before the subfloor can be nailed onto the joists, small sections of 2×12 called “blocking” must be installed.  Together with the rim joists they ensure that the floor joists won’t roll onto their flat sides where they can easily bend.  The blocking is placed along the top of the interior bearing wall at the exact place where the two floor joist spans meet and nailed perpendicularly between them.   I kept all the plumbing of the house on interior walls so I wouldn’t take any precious space away from my insulation inside the exterior walls.  My interior bearing wall being the major wall on the first floor, this meant that it had a significant amount of plumbing running through it.  The plumbing runs through the middle of the wall, and all of the DWV pipes must be vented vertically through the roof.  These pipes want to go through the middle of the interior bearing wall and exit right into the middle of my blocking!  My solution was to simply install a double set of blocking with the pipes in the middle.

Here you see the normal blocking at the outer edges of the pic and the modified blocking in the middle. The 2×6 boards at the bottom of the pic are for me to walk on until the floorboards are installed! Note how the joists from each exterior wall meet in the middle at this point.

In addition, I had planned for some of these pipes to run horizontally in the space between the floor joists.  For example, the washing machine is on the second floor, but the space I want to put it in doesn’t have a wall below it on the first floor.  If I didn’t run the pipe horizontally I would have a pipe for the dirty clothes water running through the center of the guest bedroom!  So this horizontal run would need to make a turn through the blocking so it would run in the space between the floor joists.

The pipe on the left makes a 90 degree turn to run between the floor joists while the one on the left goes straight through the blocking and will continue through the 2nd floor walls and out through the roof

All of my planning really paid off because some of the runs of ABS pipe were required to have cleanouts.  If I hadn’t installed them before running the vertical pipe up through the blocking it would have been a pain to do later.  The one you see below will be covered with a bench seat at the dining room table.  In case of a plumbing emergency the cushion can be taken off the seat and a hinged panel will provide access to the cleanout.

For a contractor, calling the plumber out before the entire house is framed is unusual.  I’m sure they would have been able to come up with a solution without breaking their routine, but I’m also pretty sure it wouldn’t have been as neat and efficient as my solution.  For me, it was very easy to stop framing for half the day and work on some plumbing so that I could finish with the blocking.  Yet another great example of the flaws in building a house with contractors…

Advice? Questions? I'd love to hear your feedback or help you out in any way I can!